As-built plans: what they are, an example, and when you need one

What an as-built plan is, an example sheet, how it differs from design drawings, and when a Philippine house needs one for a permit.

Short answer: An as-built plan is a set of drawings showing a building as it actually stands, measured on site, including every change made during and after construction. A house usually needs one before a renovation, a second floor, or a permit application for work on an existing house.

An as-built plan is a set of drawings of a building as it actually stands, measured on site, including every change made during and after construction. Design plans show what was meant to be built; as-built plans show what was built.

Someone has asked you for the as-built plans. It might be the building office, because you want to add a room, or a buyer’s bank, or the engineer looking at a second floor. And the house you are standing in was built years ago, from drawings nobody can find, and has been changed twice since.

An as-built plan puts the house as it stands back on paper.

What an as-built plan is

The same set is often called as-built drawings, and the two names mean the same thing.

An as-built set comes about in one of two ways:

  • Marked up during construction. The contractor marks every change on a copy of the permit drawings as the work goes, often in red, and the architect redraws the set from those mark-ups when the house is finished. It only works if someone marks the changes at the time.
  • Measured afterwards. For a house that is already standing, and especially an older one, someone has to measure it from scratch.

An example as-built floor plan

This is what a sheet from an as-built set looks like, and the conventions it uses. Each change from the original drawings carries a numbered revision triangle, explained in the notes. Work that has been removed is drawn dashed, so nobody mistakes it for something still standing. The title block is stamped AS-BUILT, and on a real sheet it also carries the date the house was measured.

An example as-built floor plan with three changes from the original drawings markedA floor plan of a small one-storey house: a living and kitchen area with a CR in one corner, and two bedrooms. Three numbered revision triangles mark what differs from the original drawings: a window drawn where it really is, with a dashed outline where the old drawings placed it; a former carport now used as a second bedroom; and a wall that was removed, shown dashed. A title block in the corner is stamped AS-BUILT.Livingand kitchenBedroomBedroom 2CR123AS-BUILTSheet A-1
  1. The window was moved during construction. The dashed outline is where the permit drawings put it; the solid window is where it is.
  2. The carport was enclosed and has been used as a second bedroom since. It is drawn as it is used today.
  3. A wall taken out in a later renovation, drawn dashed so nobody assumes it still carries anything.
A sample sheet, drawn to show the conventions on an imaginary house. A real set adds dimensions, a site plan, elevations, sections and the services.

What the title block shows

The title block is the box in the corner of each sheet. On an as-built set it usually gives:

  • The project name, the owner’s name and the lot address
  • The sheet name and number, so a missing sheet shows up at once
  • The scale of the drawing
  • The word AS-BUILT, and the date the house was measured
  • A revision date for each change made to the drawing
  • The name of the drafter and of the professional who signs the sheet, with the licence number where the building office asks for it

Compare the date with the year of the last change to the house. If the set was measured before an extension, it shows the house without that extension.

Design plans and as-built plans side by side

Design plansAs-built plans
What they showThe house as it is meant to be builtThe house as it stands, changes included
When they are drawnBefore constructionDuring construction from mark-ups, or afterwards by measuring
What they are based onThe brief, the lot survey and the codeThe building itself, measured on site
What they are used forThe building permit, and to build fromThe occupancy permit where the house changed, a renovation, a second floor, a sale or a loan
Who signs themThe architect and the engineers for each tradeThe same professions, each for the sheets their licence covers

As-built drawings compared with other drawings

DrawingWhat it showsWho makes it, and when
Design or permit drawingsWhat is meant to be builtThe architect and engineers, before construction, signed for the building permit
Shop drawingsHow one part is to be made or installed, such as the steel trusses, the windows or the cabinetsThe contractor or the fabricator, during construction, for the architect to check
As-built drawingsWhat was actually built, including every changeMarked up during construction, or measured afterwards
Record drawingsThe final set kept on file for the buildingUsually the designer, updating the design drawings with the contractor’s mark-ups

A floor plan is one sheet of a set. An as-built set includes floor plans, along with the other sheets listed further down this page.

Why the house rarely matches the old plans

Almost no house is built exactly to its permit drawings. A window moves because the contractor found a column in the way, a stair turns the other direction, a room gains a metre because the owner asked for it on a Saturday. Then the years add their own changes: the carport becomes a bedroom, the dirty kitchen moves outside, a sari-sari store opens in the front room.

None of that is on the original set.

So a renovation drawn over the old drawings is drawn over a house that no longer exists, and the mistakes surface on site, at the point where fixing them costs the most.

When you need one

  • Renovating or extending. New work has to meet the walls, beams and pipes that are really there.
  • Adding a second floor. Before anyone can say whether the house will carry another storey, they need to know what is holding up the first one.
  • A permit for work on an existing house. New work joins the building it is added to, so the office may ask for drawings of that building as it stands.
  • Changes made while it was being built. A house built differently from its permit drawings needs those differences drawn and put through the office before the occupancy permit, as the city checklists below show.
  • Selling, buying or borrowing. A buyer, a bank or an insurer can ask for drawings that match the property, and the ones in the drawer often do not.
  • Paperwork that was never finished. An older house that was lived in without an occupancy certificate sometimes has to be documented before that can be put right. The occupancy permit guide explains what the certificate needs.

When the building office asks for one

The Office of the Building Official, the OBO, asks for as-built plans at two points.

  • When you apply for the occupancy permit, if the house changed. Published city checklists ask for as-built plans where the work departs from the approved permit plans. Batangas City’s Office of the Building Official lists “As built plan signed and sealed by Engineer in case of alteration” on its certificate of occupancy requirements. Bacoor’s certificate of occupancy checklist (2016 revision) asks for an as-built floor plan and site development plan, signed and sealed by an architect or civil engineer, if there are changes or revisions to the approved building plans. The occupancy permit guide sets out the rest of that folder.
  • When you apply for a permit to work on an existing house. A renovation, an extension or a second floor joins the building it is added to, so the office may ask for drawings of that building as it stands.

Each office keeps its own checklist, so ask yours what it wants before the drawings are made.

Who prepares and signs it

An as-built plan is measured and drawn by an architect or an engineer. For anything going to the building office, each sheet has to be signed and sealed by the professional whose licence covers it: the architectural sheets by an architect, the structural by a civil engineer, the electrical by an electrical engineer, and the plumbing and sanitary sheets by the professionals licensed for them.

A set drawn by someone without a licence can still help you plan. It cannot go to the building office.

As-built plans by trade

Each discipline has its own as-built sheets, drawn and signed by the professional whose licence covers it, as the guide to reading a house plan sets out.

  • Architectural. Walls, doors, windows, stairs, room sizes, levels and finishes, as they stand. This is what most people mean by an as-built plan.
  • Structural. The columns, beams, slabs and roof frame that can be seen, with their sizes. What is hidden, such as the footings and the reinforcement, is marked as assumed unless it is opened up or the original structural drawings survive.
  • Electrical. The panelboard and its breakers, the circuits, and where every outlet, switch and light actually is. An as-built electrical plan matters most before an aircon unit, a second floor or a solar system is added, because each one puts new load on circuits nobody has traced.
  • Plumbing and sanitary. The water line, the drains and their cleanouts, the floor drains, and where the septic tank really sits. The septic tank guide covers the distances the tank has to keep.

How one is made

  1. A site visit. Every room is measured, usually with a tape and a laser distance meter: walls, doors and windows, ceiling heights, floor levels and wall thicknesses.
  2. The structure and services, wherever they can be seen. Columns, beams, the roof frame from the ceiling space, the electrical panel, the water line and the septic tank.
  3. Photographs, so every dimension can be checked later against what was actually there.
  4. Drafting, usually in CAD, into plans, elevations and sections at a proper scale.
  5. A return to site for anything that did not close. A room whose sides do not add up is a measurement missed, and this is the cheapest moment to catch it.
How an as-built plan is made, in five stepsFive boxes joined by arrows. A site visit measures every room; the structure and services are recorded wherever they can be seen; photographs are taken so every dimension can be checked later; the set is drafted, usually in CAD; and a return to site settles anything that did not close.Site visitevery room measuredStructure andserviceswherever they showPhotographsto check laterDraftingusually in CADReturn to sitewhat did not close
The five steps above, in order. The return to site comes last: a room whose sides do not add up is a measurement missed, and this is the cheapest moment to catch it.

Nobody can measure inside a wall or under a slab without opening it. A careful set marks what was seen and what was assumed, so nobody later sizes a beam on the strength of a guess.

What a set usually includes

  • A site plan showing the house on the lot, with the setbacks as they really are
  • Floor plans of every level
  • An elevation of each side
  • At least one section through the house
  • A roof plan
  • Electrical and plumbing layouts, where the work ahead needs them

The site plan is often the sheet that surprises people. It is where an old extension turns out to sit closer to the boundary than the rules for that lot allow, which is far better learned before a permit application than during one.

What it does not tell you

An as-built plan records what is there without saying whether it is sound. Cracks, sagging, damp and rusted reinforcement are a separate question, answered by an assessment of the structure. If you plan to build on top of what is there, have both done at the same visit.

Where this practice fits

Arktektura measures and draws as-built plans and assesses the structure in the same visit, across Pampanga, Bulacan, Tarlac, Bataan and Olongapo. The as-built plans and site assessments service covers that work. If the drawings are for a permit, the building permit guide explains what else the office will ask for, and renovate or rebuild helps once you know what you are working with. Local notes for each province are on the Pampanga, Bulacan, Tarlac, Bataan and Olongapo pages.

This guide describes common practice. Requirements differ between municipalities, so confirm what your building office needs before the drawings are made.

More guides

Start your project

Tell us where the lot is, what you want on it and roughly when. Every project is quoted after a free consultation, so the first message costs nothing and commits you to nothing.

Ask a question

Ask a question

Tell us what you are thinking about and a person will explain what a project like it involves. For a quote, use the enquiry form.